How many FTEs would it take to staff a kitchen with 12 workers who work 8 hours a day 7 days a week?

Study for the NFA Foodservice Exit Exam with our comprehensive resources, including flashcards and multiple choice questions, complete with hints and explanations to prepare you for success!

Multiple Choice

How many FTEs would it take to staff a kitchen with 12 workers who work 8 hours a day 7 days a week?

Explanation:
FTEs measure how many full-time workloads are needed based on total hours worked. To find it, add up all the hours that must be covered and divide by the weekly hours of a full-time employee. Here, 12 workers each work 8 hours per day for 7 days, so total weekly hours are 12 × 8 × 7 = 672. Dividing by the standard 40-hour work week gives 672 ÷ 40 = 16.8. So you’d need the equivalent of 16.8 full-time staff (roughly 17 full-time positions in practice). The other numbers would only fit if you used a nonstandard definition of a full-time week.

FTEs measure how many full-time workloads are needed based on total hours worked. To find it, add up all the hours that must be covered and divide by the weekly hours of a full-time employee. Here, 12 workers each work 8 hours per day for 7 days, so total weekly hours are 12 × 8 × 7 = 672. Dividing by the standard 40-hour work week gives 672 ÷ 40 = 16.8. So you’d need the equivalent of 16.8 full-time staff (roughly 17 full-time positions in practice). The other numbers would only fit if you used a nonstandard definition of a full-time week.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy